MADISONVILLE, Ky. (April 16, 2020) – Beginning on Friday, April 17, a contractor will be closing KY 2243 from Hillside Lane (MP 2.81) to U.S. 60 (MP 3.02) to construct waterline relocations as part of the Spottsville Bridge Project. The closure will be in place from 7:00 a.m. – 3:30 p.m.
The second closure for KY 2243 will begin on Monday, April 20 at 8:00 a.m. and remain in place for two weeks while the majority of this work is completed. The closure is scheduled to reopen at 8:00 a.m. on Monday, May 4. Access will be provided to local properties within the closure limits. There will not be a marked detour.
The Spottsville Bridge will remain open throughout the closures on KY 2243.
Comments