HMP&L work continues on Watson Lane this week

Henderson, KY, USA / WSON AM & FM
HMP&L work continues on Watson Lane this week


HMP&L will continue working along Watson Lane from Sunset Lane on the west through the U.S. 41 intersection to Stone Gate Drive on the East. This includes work north along Brinson Drive and adjacent to Henderson Chevy.

Work will be performed between 6 a.m. to 5 p.m. Thursday through Saturday.

Officials said while new utility poles have been set in the project, some additional concrete curing time may be needed. This week crews will be working on installing top equipment.

There will be segments of Watson Lane that may require short one lane traffic control as crews move from pole to pole. Motorists should take extra precautions through this high traffic area.

Weather conditions may affect this week’s schedule.

This work is part of an ongoing utility pole relocation/replacement project being undertaken by HMP&L and its subcontractor Groves Construction. That project is also part of Kentucky Transportation Cabinet’s upcoming Watson Lane widening project.

 